Update: New E-wood power station commissioned
On Thursday 1 December the new E-wood power station was commissioned. The commissioning was approved by AIB Vinçotte. E-Wood will convert approximately 180,000 tons of non-recyclable wood waste into energy every year. The…
E-Wood timelapse of the construction site December 2021
Watch the new timelapse of the construction.
Key figures
The new treatment facility has the capacity to incinerate approximately 180,000 tonnes of wood waste per year. Primarily construction and demolition waste, but also wood waste from container parks and the industry.
Steam supplier
E-Wood will supply steam to the industrial steam network ECLUSE, an important lever for further reducing energy consumption and CO2 emissions in the Antwerp port region and increasing the share of renewable energy.
Press release: Indaver and Veolia SUEZ build an energy from waste plant for non-recyclable wood waste in Waasland Port in Antwerp
Indaver and SUEZ have applied for a permit to build a new processing facility for non-recyclable wood waste. The investment amounts to €100 million. Christened E-Wood, or energy from wood (waste), the facility will process…