Milestones

From the start... 

The construction of the energy-from-waste plant began in the autumn of 2020. The E-Wood facility is being constructed on the Doel site so that it can make optimum use of the existing infrastructure. There is already an experienced operational team on this site, which means the operations can be integrated efficiently.

Oct 2021

Construction of delivery hall

The material will be broken down in a preliminary-treatment plant by a shredder and transported to the thermal processing facility.

Construction of delivery hall
Sept 2021

Construction

Construction
June 2021

Construction: assembling steam boiler

Construction: assembling steam boiler
Autumn 2020

Construction starts

Construction starts
Spring 2020

Permit obtained

Permit obtained
July 2019

Signing contract with building contractor

Signing contract with building contractor
Dec 2017

Start of the project

Start of the project